Attic baffles installed - now we are ready for the blown in insulation once the drywall is done. Date: 09/28/2006
Attic access through the existing attic. Date: 09/26/2006
Exterior trim and siding all done - waiting for paint. Date: 09/30/2006
Amanda and Kaley trying out the new couch in the showroom. Date: 10/01/2006
In the existing third bedroom - the main coaxial runs is behind the data/phone port. Date: 10/02/2006
Drywall hung - waiting for tape and mud. Date: 10/03/2006
Down the hallway towards the new bedroom. Date: 10/04/2006
Looking north through the entry into the family room. Date: 10/10/2006
Family room facing roughly south - drywall finished and waiting for texture. Date: 10/10/2006
Ceiling transition form the hallway to the new hallway extension upstairs. Drywall hung and finished. Date: 10/10/2006
Exterior painters making progress - almost there... Date: 10/10/2006
We must be getting close - the door has a handle! Date: 09/21/2006
Miles inspecting the new room - scouting out a good cat nap spot. Date: 09/21/2006
Surround sound speaker goes here! Date: 09/28/2006
Behind the TV in the family room - four speaker lines, cable line, data line, telephone line, and electical. Fully wired and rea Date: 09/28/2006
Stacks of drywall waiting to be hung. Date: 09/28/2006
Drywall tape, mud, and screws. Date: 09/28/2006
The small window has been replaced and trimmed out - outside is ready for paint! Date: 09/27/2006
Interior view, facing east, of the new window in the dining room. Date: 09/12/2006
The deck is already framed back into the addition nicely. Date: 09/12/2006
East wall - ready for siding. Date: 09/12/2006
All of the siding is up on the east wall - blended in nicely with the existing siding. You can see the two new windows on the le Date: 09/12/2006
One of the new windows with the primed cedar trim installed. Date: 09/12/2006
Siding going up on the north wall of the addition. Date: 09/13/2006
Inside the family room looking north. Date: 08/25/2006 OLYMPUS DIGITAL CAMERA
The closet framing for the new second floor bedroom. Date: 08/29/2006
Footer drain ties into the existing footer drain. Date: 08/29/2006
Footer drains and downspout drains installed. Date: 08/29/2006
Trusses are installed! Date: 08/31/2006
This thing is starting to really come together now! Date: 08/31/2006
We have windows! Date: 09/07/2006
The drainage passed inspection, so most of it has been covered back up! Date: 09/07/2006
This is the 4'x6' eastern facing window in the family room. Date: 09/07/2006
The new eastern view form the family room! Date: 09/07/2006
First floor joists are in! Date: 08/23/2006
First floor joists with the access hatch framed in. Date: 08/23/2006
The SIPS have arrived! Date: 08/23/2006
Electrical conduit drilled down the center of the SIPS panels. Date: 08/23/2006
Thursday morning sub-floor view. Date: 08/23/2006
Thursday morning, all we had was a sub floor! Date: 08/23/2006
By Thursday evening, the whole first floor was framed and part of the second floor joists were in. Date: 12/31/1970 OLYMPUS DIGITAL CAMERA
Side view of the completed first floor wal framing. Date: 12/31/1969 OLYMPUS DIGITAL CAMERA
Using the big forklift to "deliver" the second floor SIPS panels. Date: 12/31/1969 OLYMPUS DIGITAL CAMERA
By Friday afternoon, the whole second floor was done and waiting for trusses! Date: 12/31/1969 OLYMPUS DIGITAL CAMERA
Removing the compost pile! Obviously happened near the beginning while the foundation was being excavated. Date: 08/09/2006
We have foundation walls! Poured by the founder of the contracting company! Date: 08/19/2006
Another view of the poured foundation walls. Date: 08/19/2006
Floor joists ready for sub-floor. Date: 08/23/2006
This one shows the floor joists with the bloblocking near the outside wall. Date: 08/23/2006
The SIPS panels arrive! Date: 08/23/2006
Ready for the concrete! Date: 12/31/1969 OLYMPUS DIGITAL CAMERA
Top view of rebar in ICF form. Date: 12/31/1969 OLYMPUS DIGITAL CAMERA
ICF corner detail with all of the foundation wall rebar installed. Date: 12/31/1969 OLYMPUS DIGITAL CAMERA
Styrofoam Insulated Concrete Forms (ICF) installed and ready for the foundation wall concrete pour. Date: 12/31/1969 OLYMPUS DIGITAL CAMERA
Here is the concrete - forms are coming off one day after the pour. Date: 12/31/1969 OLYMPUS DIGITAL CAMERA
Footer forms with the corner rebar installed - ready for concrete. Date: 12/31/1969 OLYMPUS DIGITAL CAMERA
Footer forms reinforced, leveled and at the exact height. Date: 12/31/1969 OLYMPUS DIGITAL CAMERA
Rebar epoxied into the existing foundation footer. Date: 12/31/1969 OLYMPUS DIGITAL CAMERA
Garden view of the excavation and footer forms. Date: 08/09/2006
Footer forms near the deck cutoff. Date: 08/09/2006
Concrete forms for the footer after excation. Date: 08/09/2006
[-]